GROW MAHONING VALLEY
PRIORITY PROJECT #4
BUCKEYE WATER DISTRICT
(COGENTRIX PROJECT IN LISBON)
(2nd RANKING WATER PROJECT)
Request
Overview:
The request is for $9-10 million in federal
funding for
construction of a water treatment plant north of Wellsville,
Ohio in Columbiana County.
The total cost of the treatment facility is
an estimated $30 million. USDA funding
has been granted for a large portion of this project, but additional
Federal
money is needed to cover the total cost.
Project
Description:
The
project calls for
construction of a water treatment plant and raw water pump station. It includes construction of a water line from
Wellsville to the outlying rural areas including Lisbon and areas north.
Project
Cost:
The
total project cost is an
estimated $50 million. This cost
includes both the water treatment facility as well as water lines from
Wellsville north.
Economic
Impact:
Columbiana
County is the
northern most part of Appalachia.
Completion of this project, and the spin-off
jobs that it will generate, will considerably strengthen and diversify
the
industrial base of this economically distressed area.
Current
Status: 3/1/06
Recent
funding includes $250,000
through Congressman Strickland's office via the 2005 Omnibus Appr. Bill. The site along Rt. 45 between Wellsville and Lisbon has been
acquired
and environmental study completed. A
major feed line and storage tank is also completed.
Additional grant funding has been committed
by US EPA and Ohio EPA in the amount of $7.5 million. USDA has granted
$20
million toward this project. Request for $2 million from FY 2006
Appropriations
Bill made through Congressman Strickland’s office along with US
Senators
Voinovich and DeWine. Additional funding needed for completion. Plant raw water intake plans are completed.
$5 million promised in loan money. $2.2 million needed in funding to
run
waterline from Rt. 45 at Westpoint
Rd. to Lisbon.
FY2007 Appropriations Bill request has been submitted through
Congressman
Strickland and US
Senators Voinovich and DeWine for a total of $2.0 million for this
project.
Project
Contact:
Bert Dawson, Columbiana County Engineer,
at (330) 424-1740 or Greg Sherlock, Youngstown/Warren Regional Chamber,
at
330-744-2131, Ext. 15.
©